Schedule

Date Task Name and Description Completed Budget Notes and Updates
24/08/2021 Project Initiation
$100,000 - Interview Architects - Receipt of three proposals - Proposal Review - Selection/Acquisition of Architect - Payment and First Meeting
11/11/2021 Preliminary Design
$100,000 -Design Drawings Rev 0 -Review and Comment -Comment -Disposition -Design Drawings Rev 1 -Review and Comment -Comment Disposition -Design Drawings Rev 2 -Review and Comment -Comment Disposition -Design Drawings Rev 3
26/03/2022 Detailed Design
$70,000 -Technical Drawings Rev 0 -Review and Comment -Comment Disposition -Technical Drawings Rev 1 -Submission for Zoning Review -Receipt of Comments from Zoning Review -Technical Drawings Rev 2 -Re-submission for Zoning Review -Issuance of Zoning Review Certificate -Committee of Adjustments Hearing Issuance of CofA -Certificate Application for Building Permit -Issuance of Building Permit
26/08/2023 Construction
$2,000,000 Construction