24/08/2021 |
Project Initiation |
|
$100,000 |
- Interview Architects
- Receipt of three proposals
- Proposal Review
- Selection/Acquisition of Architect
- Payment and First Meeting |
11/11/2021 |
Preliminary Design |
|
$100,000 |
-Design Drawings Rev 0
-Review and Comment
-Comment -Disposition
-Design Drawings Rev 1
-Review and Comment
-Comment Disposition
-Design Drawings Rev 2
-Review and Comment
-Comment Disposition
-Design Drawings Rev 3 |
26/03/2022 |
Detailed Design |
|
$70,000 |
-Technical Drawings Rev 0
-Review and Comment
-Comment Disposition
-Technical Drawings Rev 1
-Submission for Zoning Review
-Receipt of Comments from Zoning Review
-Technical Drawings Rev 2
-Re-submission for Zoning Review
-Issuance of Zoning Review Certificate
-Committee of Adjustments Hearing
Issuance of CofA -Certificate
Application for Building Permit
-Issuance of Building Permit
|
26/08/2023 |
Construction |
|
$2,000,000 |
Construction |